Remote System Evacuation/Re-charge
All field repairs to the sealed system must start with a total dis-
charge of the system following the requirements of the Clean Air Act
of July, 1992.
Proper evacuation of the total remote system will require a three (3)
point hook-up of your manifold and hose set, (see drawing):
Point #1 - flaker receiver outlet valve
Point #2 - flaker high side service valve
Point #3 - flaker low side service valve
Evacuation:
1. With flaker power supply turned OFF disconnect and insu-
late all 3 compressor leads at the compressor. Turn power
supply on, place power switch in the on position. This will
energize (open) the Liquid Line solenoid allowing evacuation
of the Liquid Line between the solenoid and the expansion
valve(s).
2. Evacuate system to 200/250 microns or less. At this point,
there should be a holding test of five(5) minutes. You may
expect a slight loss of vacuum as normal. A rapid rise to nor-
mal atmospheric pressure indicates moisture still present in
the system. On a wet system, it will prove beneficial to use
heat lamps to warm the compressor dome and evaporator
surface during evacuation.
3. Turn flaker power switch OFF. Reconnect compressor leads.